Hunt Valley: Merrill Lynch 2nd Floor Build-Out
A full renovation of the 2nd floor of Building 1, that included the existing Halon system being removed and new electrical panels were installed. All new Merrill Lynch furniture, finishes and branding were installed. The existing NER room was reduced and reconfigured to accommodate the LOB. This NER room serviced both buildings and all floors.
Merrill Lynch Exterior Entry Renovation
An exterior renovation of the side entrance to an 8 story office building that accommodates a private entrance for Merrill Lynch employees and clientele. This included demolition of the entire side entrance,
all new concrete and stonework, steps and ADA ramp access, new vegetation and curbing.
Two 200 Ton Cooling Tower Replacements
Replacement of cooling towers on two 9 story office building in Wilmington, Delaware. All associated, disconnects, wiring, feeds and plumbing. This involved coordination of traffic control, street closures, safety and a 300 ton crane. These projects took place in winter conditions.
Bracebridge Daycare Separation
We separated the daycare electrical, BAS, Security and fire alarm systems from BOA Wilmington Complex. New utility pole, transformer and all associated electrical gear, conduit and wire were installed to create the separation. The state road was excavated along with sidewalks and building grounds to facilitate this process. The state road was replaced with approved materials and all systems were tested.
Heat Pump Replacement of Major Office Wing
The high level project scope consists of the replacement of 202 heat- pumps’, throughout all of Deerfield Wing I (floors 0, 1, 2, and 3) with new units utilizing EPA required 410 refrigerants. Also included is the reconfiguration of any ductwork, piping, or wiring needed for installation. Nearly 100% of the work effort will be required to occur off hours since the heat pumps are located above the drop ceiling in occupied work areas. Contractor will reclaim old Freon and dispose of in accordance with Bank of America and EPA regulations (with required paperwork). Each new heat pump will follow proper start-up procedures in order to ensure the heat pumps are operating as planned prior to Associates entering the space. All contractors working on-site must be CEWA Cap 2 Level Trained.
Bank of America: Portal Projects: Deerfield Complex- Wings 4, 5 & 6 and Christiana Center 1-2 & 3-4
Demolition and renovation of existing employee entrances and security offices, to accept new security entrance portal systems. This work included demolition, framing, drywall, millwork, doors and hardware, electric, fire suppression and alarm systems, HVAC, paint, carpet and ceilings. These projects happened consecutively to accommodate the new security procedures. Our team worked to complete each project on time to have minimal effect on clientele.
Corporate Escalator Replacement/Renovation
Three stories of a Newark, DE corporate center escalator system was removed renovated and replaced with a modern escalator system. Our team worked with ThyssenKrupp over a years’ time to coordinate this work along with erecting barricades and renovations of floors, walls and knee-walls.
Corporate Fire Suppression System Water Service Upgrade
This project entailed removing an existing fire pump and replacing it with a new concrete slab, fire pump and new 8” feeder for that system. We also installed a new 4” water main. The new fire pump work had to start on a Friday evening and be completed, tested, up and running by the Monday morning work day for a 9 story office building.